This example is a very small scheduling problem. We consider seven tasks where each task has a fixed duration and a fixed amount of used resource:
| Task | Duration | Resource
|
t1 | 16 | 2
|
t2 | 6 | 9
|
t3 | 13 | 3
|
t4 | 7 | 7
|
t5 | 5 | 10
|
t6 | 18 | 1
|
t7 | 4 | 11
|
The goal is to find a schedule that minimizes the completion time for
the schedule while not exceeding the capacity 13 of the resource. The
resource constraint is succinctly captured by a cumulative/2
constraint. Branch-and-bound search is used to find the minimal
completion time.
This example was adapted from [Beldiceanu & Contejean 94].
:- use_module(library(clpfd)).
schedule(Ss, End) :-
Ss = [S1,S2,S3,S4,S5,S6,S7],
Es = [E1,E2,E3,E4,E5,E6,E7],
Tasks = [task(S1,16,E1, 2,0),
task(S2, 6,E2, 9,0),
task(S3,13,E3, 3,0),
task(S4, 7,E4, 7,0),
task(S5, 5,E5,10,0),
task(S6,18,E6, 1,0),
task(S7, 4,E7,11,0)],
domain(Ss, 1, 30),
domain(Es, 1, 50),
domain([End], 1, 50),
maximum(End, Es),
cumulative(Tasks, [limit(13)]),
append(Ss, [End], Vars),
labeling([minimize(End)], Vars). % label End last
%% End of file
| ?- schedule(Ss, End).
Ss = [1,17,10,10,5,5,1],
End = 23